IllustrationSite installation is where a good factory order turns into site damage, and the fix is a delivery sequence tied to floor completion, not to shipping dates.
In short
- Sequence deliveries by floor and room type; container order puts weeks of stock in corridors.
- Confirm lift car width, height and rated load in writing before the first truck arrives.
- Hand over room by room with a signed checklist filled in on the day, not at project end.
A container arrives on a site where the floors are not finished, the lift is not commissioned and the store has no space. The furniture sits in a corridor for three weeks, loses a corner on a trolley, and is then installed by a team that has never seen the drawings. Most site damage is created before installation starts.
In short: deliver by floor and by room type, not by container; confirm lift dimensions and floor protection before the first delivery; install fixed items before loose ones; and hand over room by room with a signed checklist.
Why deliver by floor instead of by container?
Because a container is an arbitrary unit. It carries whatever the factory packed, which is usually a mix of room types for a whole building. The site needs one floor finished so the next trade can work. Mapping the container to a floor sequence costs a packing plan and saves weeks of double handling. On a 200 room project, delivering floor by floor typically halves the amount of furniture standing in corridors.
What has to be confirmed before the first truck?
Three measurements and two protections. The lift: car internal width, height and rated load; a 2,100 mm wardrobe panel does not fit a 900 mm lift door unless it goes in diagonally, and a full wardrobe carcass at 60 kg needs a lift rated for at least 630 kg with the installers inside. The stair: if there is no lift, measure the turn radius. The store: humidity and floor level. Protection: floor covering and corner guards in every corridor the goods will travel.
What is the right installation order?
Fixed items first: wardrobes, vanities, wall panels, then loose furniture, then mirrors and accessories. Within a room, the wardrobe goes in before the bed because the bed blocks access. Adjustable legs are set and levelled before the top goes on, not after. Skirting and trim last. And the room is not finished until the silicone at the wall joint is cured, which is a 24 hour item that nobody schedules.
How should site repairs be handled?
With a repair kit and a rule: no repair without a photograph and a log entry. The kit should carry the approved colour panel, matching edge band, filler in the right shade, and the lacquer in a small quantity, because a site repair with the wrong shade is worse than a visible defect. Anything structural goes back to the factory decision, not to the site carpenter.
What does a room handover contain?
A one page checklist per room: item list, door and drawer function, level check, finish check under room lighting, silicone joints, no gaps at wall, keys and locks working, and a photo of the finished room. Signed by the installer and the site manager. Rooms handed over without a checklist are the ones that generate claims six months later, because nobody can prove what was accepted.
What belongs in the installation clause? 1. Delivery sequence by floor and room type. 2. Lift and access dimensions confirmed in writing. 3. Floor and corner protection responsibility. 4. Installation order and levelling requirement. 5. Site repair rule and repair kit contents. 6. Room by room handover checklist.
The limitation: installation cannot fix a factory error, and a site team cannot be blamed for a door built 5 mm out of square. The handover checklist protects both sides only if it is filled in at the room, on the day, not reconstructed at the end of the project.