Hotel Furniture Shop Drawings: Aligning Design and Factory Illustration

Most furniture errors are made between the design drawing and the shop drawing, and two approval rounds with a written RFI process close that gap.

In short

  • The factory produces shop drawings and the designer reviews within five working days; two rounds are included.
  • Number every question and answer it on the drawing, since a verbal answer is lost within a week.
  • Freeze the revision in writing and print the revision number on every packing list.

The design intent drawing shows a wardrobe 600 mm deep. The shop drawing shows how it is built. Between those two documents sit about forty decisions nobody wrote down: where the back panel goes, which side the hinges sit on, how the top is fixed, whether the skirting is applied or recessed. Each is a chance for the two sides to disagree without noticing.

In short: the factory produces shop drawings, the designer reviews them within five working days, two rounds are included, and every question is answered in writing with a drawing number. Nothing is settled by a phone call.

Who should produce the shop drawing?

The factory, because it is the only party that knows its own machines. A designer who draws the joinery detail and sends it as a specification is describing a solution that may not be buildable at the quoted price. The designer's job is to review and approve the factory's interpretation, not to author it. When the roles reverse, the factory builds to a drawing it did not write and blames the drawing for every problem.

Why limit the approval rounds?

Because rounds have a cost and a schedule effect. Two rounds of ten days each is normal and fits inside a 45 day lead time. A third round pushes production, and an unlimited round means the drawings never freeze and the lead time never starts. Write two rounds included, a third round at a stated fee, and a hard final approval date after which changes become variation orders.

What does a written RFI process fix?

It fixes the memory problem. A verbal answer, hinge on the left, is forgotten by one of the two parties within a week. A numbered RFI with the answer attached to the drawing is a record. On one Gulf project, nine RFIs about the wardrobe door swing were resolved in writing in six days; the same discussion by phone had run for three weeks and produced forty doors on the wrong side. Number the questions, answer them on the drawing, and reissue.

Which details cause the most RFIs?

Five, consistently: the skirting treatment at the wardrobe base, the hinge side relative to the door swing, the reveal between adjacent units, the transition where a panel meets a different material, and the position of anything the site team has to cut, such as a socket or a sprinkler clearance. All five are cheap to draw and expensive to discover.

How should changes after approval be handled?

As variation orders with a price and a day impact stated within three working days. A change approved after production starts costs the scrap plus the re-setup, and that number is usually three to five times the change itself. Record the approved drawing revision on every packing list, so the site can check what version arrived.

What belongs in the drawing coordination clause? 1. Who produces shop drawings and in what format. 2. Review period and number of rounds included. 3. RFI numbering, response time and attachment rule. 4. Freeze date and the revision that becomes contractual. 5. Change order pricing and schedule impact within three working days. 6. Revision marking on packing lists.

The limitation: perfect drawings do not fix a site that changes the wall after the furniture is made. Someone has to measure the actual opening before release, and that measurement is not the designer's responsibility unless it is written into the contract.